Montgomery Street Pavement Plan in Full Effect

PavementGraph

Village of Montgomery is paving the streets with a successful Pavement Management Approach. The plan began in 2004 when the Village rated all its streets and adopted a strategic approach to paving and rehabilitation. Due to funding constraints the early program years averaged 1 mile of new paved streets per year. In 2016 a 1% local sale tax increase took effect helping invest additional funds for roadway repairs; this financial boost fueled an uptick averaging 5 miles of paved roads per year.


At the July 8th board meeting the board was updated on the pavement plan from the Village Engineer  stating “Through a combination of federal funds and increased local revenue the Village will complete 35 miles of paving, averaging about 7 miles per year from 2016-2020.”The Engineer also reported  “The Village is currently working on a new 5-year street maintenance plan that will start in 2021.”


At the conclusion of each year's program Public Works reevaluates the current 5-year plan, reviews the program with the Village Board and makes any adjustments that are needed for the next year’s program.


For more information about the Village of Montgomery street pavement plan visit their website at ci.montgomery.il.us/68/Streets-Division.

Additional Info...
Facebook Twitter Email

Other News in Village News

Village Board Celebrates Constitution Week

Posted on: September 10, 2019

Fall Community Garage Sale

Posted on: August 14, 2019

2019 Infrastructure Road Program

Posted on: April 23, 2019